Reconstruction of Various Streets - West

  • The project consists of pavement milling, roadway leveling, minor roadway reclamation, limited water service saddle replacement, casting adjustments, replacement of HMA berm/sidewalks, construction of wheelchair ramps, driveway blending, loam/seeding and roadway paving,
  • Streets Involved: Bracken Dr, Diana Dr, Fuller Dr, Gunnar Dr, Leoleis Dr, Thompson Dr, Beaudry St, Chase Rd, Flagg Rd, Nashoba Dr
  • Tentative Start Date: April 2018
  • Project Duration: 120 Days +/-
  • Contractor: Lazaro Paving Corp.