Project Name | Type of Project | Limits of Work | Status |
Reconstruction Various Roads Contract 3 |
Roadway Reconstruction |
Ames Street |
Completed |
Woodland & Vega Road Area Sewer Project |
Sewer Collection System |
Various Streets-Goodale, Woodland, Juniper and a Portion of Vega Roads |
Under Construction-Estimated Completion November 2008 |
Roadway Reconstruction-Elm Street and Locke Drive Contract 2 |
Roadway and Sidewalk Reconstruction |
Elm Street from Locke Drive to Dudley Street; Locke Drive (entire length) |
Construction Substantially Complete; Estimated Completion October 2008 |
Liberty Street Retaining Wall |
Wall installation and Sidewalk Reconstruction |
Liberty Street at Ward Park |
Estimated Start Date November 2008 |
Reconstruction of Various Roads |
Roadway and Sidewalk Overlays |
Various Streets; Goodale, Portion of Vega, Butler Circle, Portion of McNeil Circle |
Under Design-To be Bid Spring 2009 |
Maple Street Water Main Replacement |
Water Main Replacement |
Maple Street from Mill/Maple/Walker Intersection to Townline |
Under Design-To be Bid Spring 2009 |
Reconstruction Various Roads Contract 4 |
Various Roadway and Sidewalk Reconstruction |
Stevens Street from Oakcrest to Lodi Road, Union Street from Bolton Street to Hudson Street |
Under Design-To be Bid Spring 2009 |
McGee Ave. Drainage Inlet Reconstruction |
Drainage Reconstruction |
McGee Ave. Drainage Reconstruction at Inlet |
Under Design-To be Bid Summer 2009 |
Reconstruction Various Roads Contract 5 |
Various Roadway and Sidewalk Reconstruction |
Bartlett Street; Forest Street from I-495 to Bartlett Street |
Under Design-To be Bid Summer 2009 |
Reconstruction Various Roads |
Roadway Reconstruction |
Various Streets; Meadow, Spring Lane, Oakcrest Ave. and Windsor |
Under Design-To be Bid Summer 2009 |
Reconstruction Various Roads |
Roadway Reconstruction |
Various Streets-Harvard, D'Angelo Driive, Washington St. (portion), and Simpson Rd. (portion) |
Under Design-To be Bid Fall 2009 |
Hemenway Street Sidewalk Construction |
Sidewalk Construction |
Hemenway Street-Wilson Street to Langelier |
Completed Spring 2008 |
Robin Hill Street Water Main Installation |
Water Main Installation/Replacement |
Robin Hill Street; From Westerly Entrance of Sepracor to 402 Robin Hill Street |
Completed June 2008 |
Boundary Street and Robin Hill Street over Assabet River Bridge Reconstruction |
Bridge Reconstruction |
Boundary Street over Assabet River; Robin Hill Street over Assabet River |
Under Design; Anticipated Advertising Fall 2008 with Construction Starting in Spring 2009 |
Farm Road |
Reconstruction of Road, Sidewalks, Drainage and Sewer |
Farm Road-Cook Lane to Route 20 |
25% Design Under Review; Public Hearing Scheduled for October 21, 2008 at Kane School |
East Main Street |
Roadway Reconstruction and Sidewalk |
East Main Street-Main Street to Lincoln Street |
25% Design Under Review |
Route 20/Concord Road Signal Design |
Signal Design |
Route 20 and Concord Road |
25% Design Spring 2009 |
Maple Street |
Reconstruction of Road, Drainage, Sewer and Sidewalks |
Maple Street-John Street to Southborough Line |
25% Design Summer 2009 |
Sudbury Street Sewer Design |
Sewer Collection System |
Various Streets |
Under Design |
Edinboro Street Sidewalk |
Sidewalk Reconstruction |
Edinboro Street from Maple Street to Church Street |
Under Design |